Pedregalejo promenade works extended to late 2026 with an additional 857,000 euros

Málaga City Council approves a modification to the Pedregalejo promenade renovation project, adding 857,141 euros and delaying completion to late 2026.

José Manuel OrtegaJosé Manuel Ortega· · 4 min read

Málaga City Council approves a modification to the renovation project of the Pedregalejo promenade that adds 857,141 euros and delays its completion until late 2026, when it was initially expected to be ready by summer.

The comprehensive renovation of the Pedregalejo promenade, in the capital of Málaga, will not be ready by summer as anticipated. Málaga City Council has approved a modification of the project that adds 857,141.39 euros to the initial budget and delays the completion of the works until late 2026.

This was announced on Monday by the councillors for Urban Planning, Carmen Casero; Environmental Sustainability, Penélope Gómez, and the district councillor for the East, Carlos Conde. The new actions focus on improving sanitation infrastructures and other services included in the project.

An investment exceeding 6.5 million

The modification of the project, currently in processing, raises the total budget for the work to over 6.58 million euros. The initial contract was awarded for 5,725,039.62 euros, to which 857,141.39 euros (including VAT) are now added.

The works began on 6 October 2025 with a planned duration of ten months. However, the City Council has confirmed that, following the approval of the extension due to these improvements, the expectation is that the works will be completed by late 2026. Local residents and business owners will need to be patient for a few more months.

Improvements in sanitation and new pumping station

One of the main updates affects the sanitation network. The project incorporates improvements in the new wastewater pumping station that will replace the current one located in plaza Miguelito el Cariñoso. New pumping equipment, a rotary screen, a deflector screen, a deodorization system, acoustic insulation, and anti-vibration membranes will be installed to reduce the impact of the facilities.

Additionally, following the recommendations of Emasa, new sections of pipes and valves will also be installed to improve the supply and irrigation network. This measure aims to prevent future supply issues in a very busy area.

Drainage and lighting adapted to Coast requirements

The City Council will also modify the planned system to improve the drainage of Venezuela Street. The initial project included a pipe with a diameter of 800 millimeters, but ultimately two conduits of 600 millimeters will be executed using the jacking technique, aiming to ensure a more effective evacuation of rainwater.

Regarding lighting, the authorization from the Coast Demarcation has forced a modification of the initially proposed solution. The planned 12-meter-high luminaires will be replaced with eight-meter poles to avoid underground conduits along the beach. Additionally, conduits will be installed to facilitate future light points for the speteteros of the hospitality establishments. The owners of the beach bars breathe a sigh of relief: the sardine skewers will continue to be a night-time attraction.

Unified kiosks and an adapted toilet

The project also includes improvements requested by the kiosk owners of the promenade. The five existing establishments will have a uniform model, built with a galvanized metal structure, folding doors, counters, and a perimeter loft. A more uniform image that aims to modernize the promenade.

Among the new features is the construction of an adapted toilet for ostomized individuals, a demand from patient groups that until now had no response in this area of the city.

Segmented works to minimize disruptions

The City Council reminds that the work continues to be developed in phases to minimize the impact on pedestrian traffic and hospitality activities. Currently, different sections of the promenade are under construction, including the building of the new pumping station, works on Venezuela Street, and the paving of the eastern sector. In the more advanced sections, only tasks such as the installation of pergolas, finishing touches on the riverbank wall, and the urbanization of the Varadero square remain.

According to the City Council, the comprehensive renovation of the promenade will create more space for pedestrians, improve accessibility, reorganize the hospitality terraces, and provide the area with new urban furniture, lighting, and resting areas. Residents of Pedregalejo will have to wait until the end of the year to enjoy a renovated promenade, but the wait promises to be worth it.