The works of the Málaga Metro have taken a new step with the start of the execution of diaphragm walls in the third section, located between Eugenio Gross and Blas de Lezo. This progress occurred on 16 November 2026.
Disruptions to work schedules
The Citizen Attention Office has previously informed residents about these works, which could cause temporary disruptions to work schedules. The construction of this section will require the possibility of extending operating hours.
The work on the lateral walls of the tunnel must be carried out continuously until each complete cycle is finished. This includes the initial excavation, the introduction of rebar, the concreting, and the extraction of the tube used to pour the concrete.
Excavation and supervision details
The excavation is carried out longitudinally and in two phases. The first descent reaches half the depth of the wall, followed by an intermediate test. Then, work continues until the total depth of 30 meters is achieved.
The Public Works Agency of the Junta de Andalucía will supervise the work of the construction consortium to minimize inconvenience to residents. This phase of construction follows the relocation and installation of the diaphragm wall machine and its auxiliary equipment.
The machines will operate on Eugenio Gross street, between Martínez de la Rosa and Velarde, for an approximate period of three months. Additionally, the development of works in the other sections of the extension is being closely monitored.
The works of the Málaga Metro, which will extend to the future Hospital Virgen de la Esperanza, are co-financed by EU Feder funds and cover a route of 1.8 kilometers that will include three stations.